For Air compressors that have start/stop or load/unload controls, there is an easy way to estimate the amount of leakage in the system.

The Leak test method involves starting the compressor when there are no demands on the system. A number of measurements are taken to determine the average time it takes to load and unload the air compressor.
Total leakage in percentage in air network can be calculated as:

 Leakage (%) = (T x 100) / (T + t )


 where,
 T = on-load time, 
  t = off-load time.

Leakage quantity will be expressed in terms of the percentage of compressor capacity lost.

The percentage lost to leakage should be less than 10% in a well maintained system. 



Poorly maintained systems can have losses as high as 20 to 30 percent of air capacity and power.

Popular posts from this blog

How to find out length of holding tube in pasteurizer?

Pasteurization requires that the milk is in custody for a specified time. The appropriate length for the holding tube can be calculated by the flow rate (Q) of milk and the diameter (D) of the holding tube using the formula: Length of holding tube, L = Q x holding time/A x Î· A = Area = pi/4 x sqr D Where an efficiency factor, η, of 0.85 is used in the model.

Specific power consumption of Air compressor

Specific Power Consumption   Specific power consumption is the ratio of the power consumed by an engine to a certain force such as the amount of output the engine (equipment) produces. It allows engines (equipments) of all different sizes to be compared to see which is the most power efficient. It allows manufacturers to see which engine (equipment) will use the least power while still producing a high amount of output. Specific power consumption of Air compressor The ratio of power consumption (in KW) to the volume delivered at ambient conditions. Specific power consumption= Actual power consumed by the compressor/Measured free air delivery If the measured flow is 250 m3/hr and actual power consumption is 30KW. Then Specific power requirement = 20 KW/250 m3/hr